Hi,
When I exported the plan, I found that if “Should not start before…” is set in the summary task and is not set in the leaf task, the summary task in the exported plan will lose this restriction type and restriction …...columns when exported to MPP or to XML format ? Jiangqiming December...10:40am 10 Hi The export format is mpp The export effect in our current...